Update on Menai Suspension Bridge works progress

  • Tweet
Wednesday, 30 August, 2023
  • Local News
Menai

Work to fix the Menai Bridge will be finished by the 200th anniversary of its construction in 2026, Ynys Môn MP Virginia 
Crosbie has been told in an update.


Virginia met with Welsh Government, the bridge’s operator UK Highways A55 Ltd and the contractor Spencer Group 
to hear about the schedule of works to ensure the bridge can remain in use following a very disruptive closure period 
earlier this year.


The MP was told work commenced this month and hanger replacement works are on schedule to begin on the 4th 
September.


Completion will be October 2024 followed by a painting programme to start at the back end of the replacement works 
and continue to August 2025. Both lanes should reopen in March 2025.


Work will be suspended and traffic management lifted over the Christmas periods. The work is being paid for by UK 
Highways A55.


“I thank everyone for a comprehensive update on what will happen and I know islanders and those who travel regularly 
to Anglesey will want to know what will happen over the next two years,” said Virginia.


“There is going to be disruption really until 2025 to ensure the bridge is safe and fit for purpose ahead of its 
200th anniversary. This is something for the island to celebrate but it also very much highlights how we are relying on 
a structure built in the early 19th century to connect us.


“This needs to change and it’s why I support a third Menai crossing. I urge Labour in Cardiff to think again about its 
ridiculous ban on road building, listen to islanders and get a third crossing built.”

You may also be interested in

third crossing

Fighting for a Third Menai Crossing

As part of the Welsh road infrastructure bridges across the Menai Strait fall under the remit of the Welsh Government.
Menai Bridge High Street December 2022

Survey of Businesses affected by the closure of the Menai Suspension Bridge

In the Senedd on 11 January 2023 Sam Rowlands MS raised concerns about businesses struggling due to reduced footfall and trade in Menai Bridge. In response, the Welsh Government’s Deputy Minister for Climate Change, Lee Waters MS, said “…what's been very interesting is that the data, rather than t
LJ4LP

Local Jobs for Local People

The UK Government was elected on a manifesto to take us out of the EU and level up the UK.  Levelling up means making sure that areas of the UK that have been underfunded in recent years – like Ynys Môn – get inward investment so that our young people have the same opportunities as more prosper

My Plan for Ynys Môn: 2019-2024

.
H𝗼𝗹𝘆𝗵𝗲𝗮𝗱 & 𝗔𝗻𝗴𝗹𝗲𝘀𝗲𝘆 𝗠𝗮𝗶𝗹 - 𝗠𝗮𝗸𝗶𝗻𝗴 𝗮 𝗱𝗶𝗳𝗳𝗲𝗿𝗲𝗻𝗰𝗲 𝗮𝘁 𝗲𝘃𝗲𝗿𝘆 𝗹𝗲𝘃𝗲𝗹 𝗮𝗹𝗼𝗻𝗴𝘀𝗶𝗱𝗲 𝗰𝗼𝗺𝗺𝘂𝗻𝗶𝘁𝗶𝗲𝘀

𝗛𝗼𝗹𝘆𝗵𝗲𝗮𝗱 & 𝗔𝗻𝗴𝗹𝗲𝘀𝗲𝘆 𝗠𝗮𝗶𝗹 - 𝗠𝗮𝗸𝗶𝗻𝗴 𝗮 𝗱𝗶𝗳𝗳𝗲𝗿𝗲𝗻𝗰𝗲 𝗮𝘁 𝗲𝘃𝗲𝗿𝘆 𝗹𝗲𝘃𝗲𝗹 𝗮𝗹𝗼𝗻𝗴𝘀𝗶𝗱𝗲 𝗰𝗼𝗺𝗺𝘂𝗻𝗶𝘁𝗶𝗲𝘀

Wednesday, 22 May, 2024
In this column I usually focus on the ‘bigger picture’ part of my role:   fighting to secure Anglesey Freeport in Westminster because I know how much our young people need the good quality, well paid jobs this will bring,  badgering Ministers, raising the profile of new nucl

Show only

  • Articles
  • European News
  • Local News
  • Opinions
  • Reports
  • Senedd News
  • Speeches
  • Speeches in Parliament
  • Westminster News
  • Written Questions News

Virginia Crosbie Former Conservative Member of Parliament for Ynys Môn

Footer

  • About RSS
  • Accessibility
  • Cookies
  • Privacy
  • About Virginia Crosbie
  • My Plan for Ynys Môn: 2019-2024
ConservativesPromoted by Bethan Davies on behalf of Virginia Crosbie, both c/o PO Box 85, Holyhead LL77 9BZ
Copyright 2025 Virginia Crosbie Former Conservative Member of Parliament for Ynys Môn. All rights reserved.
Powered by Bluetree